Land-use attorney of record · 14 unique cases
24
Hearings
14
Cases
11
Concluded
54.5%
Approved of concluded
2016–2020
Active
0
Since 2024

The record, at case level

Of Bill E. Couch’s 14 unique cases, 11 have concluded — reached a Planning Commission or ZAP decision — and 6 of those ended in approval at their final hearing: 54.5%.

Postponement is a clock, not a verdict: of the 1 concluded cases postponed at least once, 1 still ended in approval (100.0%).

Counted once per case, not once per hearing: a case postponed several times before approval would otherwise read as several losses and one win.

Hearings by year

Bill E. Couch: hearings by year2016: 2, 2017: 0, 2018: 9, 2019: 5, 2020: 8492’16’179’185’198’20

Outcome distribution

Bill E. Couch: outcomesApproved: 9 (38%), Postponed: 3 (12%), Denied: 6 (25%), No decision: 6 (25%)38%12%25%25%Approved 9Postponed 3Denied 6No decision 6

Hearing timeline

Hearing dateOutcomeDistrictFirm
2020-11-24ApprovedD2Carlson, Brigance & Doering, Inc
2020-11-10ApprovedD2Carlson, Brigance & Doering, Inc
2020-08-25ApprovedD8Carlson, Brigance & Doering, Inc
Pro · Full record
The complete 24-hearings record is a Pro feature. See what Pro unlocks →

Firm

Carlson, Brigance & Doering, Inc

Where they practice

D2 11D8 5D1 3D9 1

Hearing-level rates, for comparison

Postponement rate vs the fieldBill E. Couch: 17%, Field median: 44%Bill E. Couch17%Field median44%
Approval rate 50.0% — above the field (46.1%) by 3.9 pts.

At the hearing level every appearance counts, so a case postponed N times adds N postponements and one decision. Hearing-level approval-of-decided is 50.0% (vs the field’s 46.1%) and postponement is 16.7% — both far from the case-level figure above, for exactly that reason. Two stages, two denominators: these are commission-stage outcomes (approve vs. postpone/deny at the Planning Commission or ZAP hearing), not the City Council vote. Once a Commission-recommended case reaches Council it is approved in the high-90s%, so a low commission-stage approval rate reflects strategic postponement, not defeat.